What is land filling in Dholera and what does it earn?
What land filling earns, and why it is needed
Much of the Dholera plain is low-lying and has to be raised and levelled before anything can stand on it. The development company charges buyers to do that work, and this page tells you what it billed for it in each audited year. The answer is 4 006.74 INR lakh for the year ended 31 March 2025, and this page carries two audited years of it so you can see the direction as well as the level.
The figure, and when it was published
Income from filling and levelling plots
4 006.74INR lakh
Published for the year ended 31 March 2025 in dicdl_ar25.pdf, p92 (printed p81). The tag OFFICIAL means this is a figure the source itself prints, not one this site has worked out.
Note 21 Revenue from operation
Source: Dholera Industrial City Development Limited, 9th Annual Report 2024-25. Reference: dicdl_ar25.pdf, p92 (printed p81). Reading date: the year ended 31 March 2025.
Every published figure, in order
Income from filling and levelling plots: 2 dated readings
| As on | Value | Unit | As printed in the source | Tag | Source file and page | CK |
|---|---|---|---|---|---|---|
| FY 2023-24 | 0 | INR lakh | Land filling revenue | OFFICIAL | AR_FY2023-24.pdf, p95 (printed p89) | |
| FY 2024-25 | 4 006.74 | INR lakh | no text layer | OFFICIAL | dicdl_ar25.pdf, p92 (printed p81) | |
| Standing reading | 4 006.74 | INR lakh | no text layer | OFFICIAL | dicdl_ar25.pdf, p92 (printed p81) |
Sources: AR_FY2023-24.pdf, dicdl_ar25.pdf. Readings: 2. Range: 31 March 2024 to 31 March 2025.
What this figure actually counts
Much of the Dholera plain sits low and has to be raised and levelled before anything can be built on it. The company charges for doing that work on a buyer's plot, and this line is what it billed for it.
What this figure does not tell you
This line was nil in the earlier year and substantial in the later one, which reflects when the work was billed rather than when any particular plot was filled.
Definition written by this register. The quantity, its unit and its date are the source's; the explanation is ours and carries no figures of its own.
When it changed
This quantity changed 1 time across the readings held here. Each row is a change between two consecutive published readings, so the change happened somewhere inside that window and cannot be dated more finely from these sources.
Income from filling and levelling plots: every recorded change
| Between | From | To | Change | Unit | Source pages |
|---|---|---|---|---|---|
| 31.03.2024 to 31.03.2025 | 0 | 4 006.74 | +4 006.74 | INR lakh | AR_FY2023-24.pdf p95 to dicdl_ar25.pdf p92 |
Computed from the dataset by comparing consecutive published readings. Nothing is interpolated between two readings.
Figures worth reading beside this one
Readings that belong beside this one
| Quantity | Latest value | Unit | As on | Source |
|---|---|---|---|---|
| Revenue from operations | 10 613.82 | INR lakh | 31.03.2025 | dicdl_ar25.pdf, p68 (printed p57) |
| Project expense incurred | 22 795.09 | INR lakh | 31.03.2025 | dicdl_ar25.pdf, p68 (printed p57) |
Latest reading for each related quantity, with its own date and source page.