Metric / dicdl-total-expenses

What does the Dholera development company spend in a year?

What the company charged against income

This is everything the company set against its income in one financial year, including project costs, staff pay and depreciation. It is an accounting total, and it is not the same thing as money that went into the ground, which no source in this register publishes. The answer is 12 835.25 INR lakh for the year ended 31 March 2025, and this page carries three audited years of it so you can see the direction as well as the level.

01

The figure, and when it was published

DICDL total expenses

12 835.25INR lakh

Published for the year ended 31 March 2025 in dicdl_ar25.pdf, p68 (printed p57). The tag OFFICIAL means this is a figure the source itself prints, not one this site has worked out.

Source: Dholera Industrial City Development Limited, 9th Annual Report 2024-25. Reference: dicdl_ar25.pdf, p68 (printed p57). Reading date: the year ended 31 March 2025.

02

Every published figure, in order

DICDL total expenses, 3 dated readingsRecorded values between 31 March 2023 and 31 March 2025, in INR lakh. Every plotted point is a published reading; nothing between two points is interpolated.020 00040 00060 00031.03.2331.03.2431.03.25REPORT DATEINR LAKHDICDL total expenses, 3 dated readingsRecorded values between 31 March 2023 and 31 March 2025, in INR lakh. Every plotted point is a published reading; nothing between two points is interpolated.020 00040 00060 00031.03.2331.03.2431.03.25REPORT DATEINR LAKH
Each square is one published figure and the line simply joins them. Points sit at their true dates, so a wide gap across the page is a gap in the reporting rather than a slow month.

DICDL total expenses: 3 dated readings

DICDL total expenses: 3 dated readings
As onValueUnitAs printed in the sourceTagSource file and pageCK
FY 2022-232 361.71INR lakh2,361.71OFFICIALAR_FY2023-24.pdf, p18 (printed p12)
FY 2023-2449 254.8INR lakh49,254.80OFFICIALAR_FY2023-24.pdf, p18 (printed p12)
FY 2024-2512 835.25INR lakhno text layerOFFICIALdicdl_ar25.pdf, p68 (printed p57)
Standing reading12 835.25INR lakhno text layerOFFICIALdicdl_ar25.pdf, p68 (printed p57)

Sources: AR_FY2023-24.pdf, dicdl_ar25.pdf. Readings: 3. Range: 31 March 2023 to 31 March 2025.

03

What this figure actually counts

Everything charged against income in the year, including the change in inventory of land and work in progress. That inventory movement can be negative, which is why this line can fall even in a year when the company spends heavily on development: capitalised development cost sits on the balance sheet rather than in this total.

What this figure does not tell you

Two comparative figures inside this total were restated in the following year's report. This register keeps the figure each report printed rather than choosing between them.

Definition written by this register. The quantity, its unit and its date are the source's; the explanation is ours and carries no figures of its own.

04

When it changed

This quantity changed 2 times across the readings held here. Each row is a change between two consecutive published readings, so the change happened somewhere inside that window and cannot be dated more finely from these sources.

DICDL total expenses: every recorded change

DICDL total expenses: every recorded change
BetweenFromToChangeUnitSource pages
31.03.2023 to 31.03.20242 361.7149 254.8+46 893.09INR lakhAR_FY2023-24.pdf p18 to AR_FY2023-24.pdf p18
31.03.2024 to 31.03.202549 254.812 835.25-36 419.55INR lakhAR_FY2023-24.pdf p18 to dicdl_ar25.pdf p68

Computed from the dataset by comparing consecutive published readings. Nothing is interpolated between two readings.

05

Figures worth reading beside this one

Readings that belong beside this one

Readings that belong beside this one
QuantityLatest valueUnitAs onSource
Project expense incurred22 795.09INR lakh31.03.2025dicdl_ar25.pdf, p68 (printed p57)
Total income19 850.33INR lakh31.03.2025dicdl_ar25.pdf, p68 (printed p57)