Dholera Progress Record

Official figures, with the date and the page they came from

Newest figure on this site 30 June 2026
Metric / dicdl-trade-payables

How much does the Dholera company still owe its contractors?

Bills from contractors still unpaid

This page tells you how much work had been done for the Dholera development company, and billed to it, without being paid for by the end of the year. It rises when more building is going on, so it is a rough and imperfect signal of activity. The answer is 7 739.79 INR lakh for at 31 March 2025, and this page carries three audited years of it so you can see the direction as well as the level.

01

The figure, and when it was published

Bills the company has not yet paid

7 739.79INR lakh

Published for at 31 March 2025 in dicdl_ar25.pdf, p67 (printed p56). The tag OFFICIAL means this is a figure the source itself prints, not one this site has worked out.

Source: Dholera Industrial City Development Limited, 9th Annual Report 2024-25. Reference: dicdl_ar25.pdf, p67 (printed p56). Reading date: at 31 March 2025.

02

Every published figure, in order

Bills the company has not yet paid, 3 dated readingsRecorded values between 31 March 2023 and 31 March 2025, in INR lakh. Every plotted point is a published reading; nothing between two points is interpolated.02 0004 0006 0008 00031.03.2331.03.2431.03.25REPORT DATEINR LAKHBills the company has not yet paid, 3 dated readingsRecorded values between 31 March 2023 and 31 March 2025, in INR lakh. Every plotted point is a published reading; nothing between two points is interpolated.02 0004 0006 0008 00031.03.2331.03.2431.03.25REPORT DATEINR LAKH
Each square is one published figure and the line simply joins them. Points sit at their true dates, so a wide gap across the page is a gap in the reporting rather than a slow month.

Bills the company has not yet paid: 3 dated readings

Bills the company has not yet paid: 3 dated readings
As onValueUnitAs printed in the sourceTagSource file and pageCK
FY 2022-231 743.56INR lakh1,743.56OFFICIALAR_FY2023-24.pdf, p63 (printed p57)
FY 2023-241 068.86INR lakh1,068.86OFFICIALAR_FY2023-24.pdf, p63 (printed p57)
FY 2024-257 739.79INR lakhno text layerOFFICIALdicdl_ar25.pdf, p67 (printed p56)
Standing reading7 739.79INR lakhno text layerOFFICIALdicdl_ar25.pdf, p67 (printed p56)

Sources: AR_FY2023-24.pdf, dicdl_ar25.pdf. Readings: 3. Range: 31 March 2023 to 31 March 2025.

03

What this figure actually counts

Trade payables is work already done for the company and billed to it, that it had not paid for by the year end. This line covers suppliers other than the smallest firms, which the law requires to be reported separately.

What this figure does not tell you

Unpaid bills at a year end are a snapshot, not a debt problem, and they usually rise when more work is being done. They cannot be read as a measure of construction volume on their own.

Definition written by this register. The quantity, its unit and its date are the source's; the explanation is ours and carries no figures of its own.

04

When it changed

This quantity changed 2 times across the readings held here. Each row is a change between two consecutive published readings, so the change happened somewhere inside that window and cannot be dated more finely from these sources.

Bills the company has not yet paid: every recorded change

Bills the company has not yet paid: every recorded change
BetweenFromToChangeUnitSource pages
31.03.2023 to 31.03.20241 743.561 068.86-674.7INR lakhAR_FY2023-24.pdf p63 to AR_FY2023-24.pdf p63
31.03.2024 to 31.03.20251 068.867 739.79+6 670.93INR lakhAR_FY2023-24.pdf p63 to dicdl_ar25.pdf p67

Computed from the dataset by comparing consecutive published readings. Nothing is interpolated between two readings.

05

Figures worth reading beside this one

Readings that belong beside this one

Readings that belong beside this one
QuantityLatest valueUnitAs onSource
Total liabilities66 374.34INR lakh31.03.2025dicdl_ar25.pdf, p67 (printed p56)
Project expense incurred22 795.09INR lakh31.03.2025dicdl_ar25.pdf, p68 (printed p57)

Latest reading for each related quantity, with its own date and source page.