How big is the Dholera solar park meant to be?
How big the solar park is meant to be
This is the full size the Dholera solar park is planned to reach, measured in megawatts. It is the number every completion figure should be read against, and it has not been revised once across the whole period covered here. The answer today is 1 000 MW, as at 30 June 2026. It has not changed once in the 8 monthly reports held here, going back to 30 June 2025.
The figure, and when it was published
Planned capacity of the Dholera Solar Park
1 000MW
Published for 30 June 2026 in dmu-latest.pdf, p1. The tag OFFICIAL means this is a figure the source itself prints, not one this site has worked out.
Source: NICDC/DPIIT 'Proforma for Reporting to the Delivery Monitoring Unit - Industrial Corridor Projects', as-on 30.06.2026. Reference: dmu-latest.pdf, p1. Reading date: 30 June 2026.
Every published figure, in order
Planned capacity of the Dholera Solar Park: 8 dated readings
| As on | Value | Unit | As printed in the source | Tag | Source file and page | CK |
|---|---|---|---|---|---|---|
| 30.06.2025 | 1 000 | MW | 1,000 | OFFICIAL | dmu-2025-06-30.pdf, p1 | |
| 31.08.2025 | 1 000 | MW | 1,000 | OFFICIAL | dmu-2025-08-31.pdf, p1 | |
| 30.09.2025 | 1 000 | MW | 1,000 | OFFICIAL | dmu-2025-09-30.pdf, p1 | |
| 31.10.2025 | 1 000 | MW | 1,000 | OFFICIAL | dmu-2025-10-31.pdf, p1 | |
| 30.11.2025 | 1 000 | MW | 1,000 | OFFICIAL | dpiit-nicdc-2025-11.pdf, p1 | |
| 31.01.2026 | 1 000 | MW | 1,000 | OFFICIAL | dmu.pdf, p1 | |
| 31.05.2026 | 1 000 | MW | 1,000 | OFFICIAL | dmu-2026-05-31.pdf, p1 | |
| 30.06.2026 | 1 000 | MW | 1,000 | OFFICIAL | dmu-latest.pdf, p1 | |
| Standing reading | 1 000 | MW | 1,000 | OFFICIAL | dmu-latest.pdf, p1 |
Sources: dmu-2025-06-30.pdf, dmu-2025-08-31.pdf, dmu-2025-09-30.pdf, dmu-2025-10-31.pdf, dmu-2026-05-31.pdf, dmu-latest.pdf, dmu.pdf, dpiit-nicdc-2025-11.pdf. Readings: 8. Range: 30 June 2025 to 30 June 2026.
What this figure actually counts
The full planned capacity of the solar park, which is the denominator every commissioned figure should be read against. It is a plan number and it has never moved in any edition of the report, which is itself the finding: the plan has not been revised upward or downward across the whole period covered here.
What this figure does not tell you
A planned capacity is not a built one. The commissioned figure is reported separately and is the only capacity the source describes as delivered.
How the source words it
Out of the X MW of Solar ParkWording as it appears in the Delivery Monitoring Unit proforma. X and N stand for the printed figures.
Definition written by this register. The quantity, its unit and its date are the source's; the explanation is ours and carries no figures of its own.
Why it has not changed
This quantity did not change in any of the 8 readings held here, from 30 June 2025 to 30 June 2026. That is a finding rather than an absence of one: the same figure was re-published every time the report was issued. A register records repetition as carefully as it records movement, because a figure that has not moved in a year is the answer to a question people keep asking about this project.
Computed from the dataset by comparing consecutive published readings. Nothing is interpolated between two readings.
Figures worth reading beside this one
Readings that belong beside this one
| Quantity | Latest value | Unit | As on | Source |
|---|---|---|---|---|
| Solar capacity commissioned | 300 | MW | 30.06.2026 | dmu-latest.pdf, p1 |
Latest reading for each related quantity, with its own date and source page.