Dholera Progress Record

Official figures, with the date and the page they came from

Newest figure on this site 30 June 2026
Metric / approved-infrastructure-package-count

How many construction contracts is Dholera's infrastructure split into?

How many contracts the work was split into

The approved infrastructure money is divided into a fixed number of tender packages, which are the separate contracts the work is put out to bid in. This page gives that number, and explains why the reports never tell you what is inside any one of them. The answer today is 5 packages, as at 30 June 2026. It has not changed once in the 8 monthly reports held here, going back to 30 June 2025.

01

The figure, and when it was published

Number of approved infrastructure packages

5packages

Published for 30 June 2026 in dmu-latest.pdf, p1. The tag OFFICIAL means this is a figure the source itself prints, not one this site has worked out.

Printed as a word in the source ('five'); digit form is a transcription of that word, not a conversion.

Source: NICDC/DPIIT 'Proforma for Reporting to the Delivery Monitoring Unit - Industrial Corridor Projects', as-on 30.06.2026. Reference: dmu-latest.pdf, p1. Reading date: 30 June 2026.

02

Every published figure, in order

Number of approved infrastructure packages, 8 dated readingsRecorded values between 30 June 2025 and 30 June 2026, in packages. Every plotted point is a published reading; nothing between two points is interpolated.44.555.5630.06.2531.08.2531.10.2531.01.2630.06.26REPORT DATEPACKAGESNumber of approved infrastructure packages, 8 dated readingsRecorded values between 30 June 2025 and 30 June 2026, in packages. Every plotted point is a published reading; nothing between two points is interpolated.44.555.5630.06.2530.11.2530.06.26REPORT DATEPACKAGES
Each square is one published figure and the line simply joins them. Points sit at their true dates, so a wide gap across the page is a gap in the reporting rather than a slow month.

Number of approved infrastructure packages: 8 dated readings

Number of approved infrastructure packages: 8 dated readings
As onValueUnitAs printed in the sourceTagSource file and pageCK
30.06.20255packagesfiveOFFICIALdmu-2025-06-30.pdf, p1
31.08.20255packagesfiveOFFICIALdmu-2025-08-31.pdf, p1
30.09.20255packagesfiveOFFICIALdmu-2025-09-30.pdf, p1
31.10.20255packagesfiveOFFICIALdmu-2025-10-31.pdf, p1
30.11.20255packagesfiveOFFICIALdpiit-nicdc-2025-11.pdf, p1
31.01.20265packagesfiveOFFICIALdmu.pdf, p1
31.05.20265packagesfiveOFFICIALdmu-2026-05-31.pdf, p1
30.06.20265packagesfiveOFFICIALdmu-latest.pdf, p1
Standing reading5packagesfiveOFFICIALdmu-latest.pdf, p1

Sources: dmu-2025-06-30.pdf, dmu-2025-08-31.pdf, dmu-2025-09-30.pdf, dmu-2025-10-31.pdf, dmu-2026-05-31.pdf, dmu-latest.pdf, dmu.pdf, dpiit-nicdc-2025-11.pdf. Readings: 8. Range: 30 June 2025 to 30 June 2026.

03

What this figure actually counts

The approved trunk infrastructure value is split into a fixed number of tender packages. The source prints the number as a word rather than a numeral, and the digit form used here is a transcription of that word, not a conversion of a figure. The reports never name the packages, never price them individually and never report progress on any one of them.

What this figure does not tell you

Because the packages are unnamed and unpriced individually, a reader cannot tell which package covers roads, which covers water, or how far any single one has got.

How the source words it

divided into N packages for activation areaWording as it appears in the Delivery Monitoring Unit proforma. X and N stand for the printed figures.

Definition written by this register. The quantity, its unit and its date are the source's; the explanation is ours and carries no figures of its own.

04

Why it has not changed

This quantity did not change in any of the 8 readings held here, from 30 June 2025 to 30 June 2026. That is a finding rather than an absence of one: the same figure was re-published every time the report was issued. A register records repetition as carefully as it records movement, because a figure that has not moved in a year is the answer to a question people keep asking about this project.

Computed from the dataset by comparing consecutive published readings. Nothing is interpolated between two readings.

05

Figures worth reading beside this one

Readings that belong beside this one

Readings that belong beside this one
QuantityLatest valueUnitAs onSource
Approved tender package value2 784.83INR crore30.06.2026dmu-latest.pdf, p1

Latest reading for each related quantity, with its own date and source page.