Metric / 8 dated readings
Approved value of trunk infrastructure tender packages
Approved value of trunk infrastructure tender packages was recorded at 2 784.83 INR crore in the Delivery Monitoring Unit report as on 30 June 2026, tagged OFFICIAL. The same quantity appears in 8 reports between 30 June 2025 and 30 June 2026. It never moved. Every reading below carries its source file and page.
The standing reading
2 784.83INR crore
Approved value of trunk infrastructure tender packages, 30 June 2026, tagged OFFICIAL. Recorded in dmu-latest.pdf, p1.
Approved tender package value. NOT expenditure incurred; the report gives no expenditure-to-date figure for Dholera.
Source: NICDC/DPIIT 'Proforma for Reporting to the Delivery Monitoring Unit - Industrial Corridor Projects', as-on 30.06.2026. Reference: dmu-latest.pdf, p1. Reading date: 30 June 2026.
The series, reading by reading
| As on | Value | Unit | As printed in the source | Tag | Source file and page | CK |
|---|---|---|---|---|---|---|
| 30.06.2025 | 2 784.83 | INR crore | Rs. 2,784.83 Crore | OFFICIAL | dmu-2025-06-30.pdf, p1 | |
| 31.08.2025 | 2 784.83 | INR crore | Rs. 2,784.83 Crore | OFFICIAL | dmu-2025-08-31.pdf, p1 | |
| 30.09.2025 | 2 784.83 | INR crore | Rs. 2,784.83 Crore | OFFICIAL | dmu-2025-09-30.pdf, p1 | |
| 31.10.2025 | 2 784.83 | INR crore | Rs. 2,784.83 Crore | OFFICIAL | dmu-2025-10-31.pdf, p1 | |
| 30.11.2025 | 2 784.83 | INR crore | Rs. 2,784.83 Crore | OFFICIAL | dpiit-nicdc-2025-11.pdf, p1 | |
| 31.01.2026 | 2 784.83 | INR crore | Rs. 2,784.83 Crore | OFFICIAL | dmu.pdf, p1 | |
| 31.05.2026 | 2 784.83 | INR crore | Rs. 2,784.83 Crore | OFFICIAL | dmu-2026-05-31.pdf, p1 | |
| 30.06.2026 | 2 784.83 | INR crore | Rs. 2,784.83 Crore | OFFICIAL | dmu-latest.pdf, p1 | |
| Standing reading | 2 784.83 | INR crore | Rs. 2,784.83 Crore | OFFICIAL | dmu-latest.pdf, p1 |
Sources: dmu-2025-06-30.pdf, dmu-2025-08-31.pdf, dmu-2025-09-30.pdf, dmu-2025-10-31.pdf, dmu-2026-05-31.pdf, dmu-latest.pdf, dmu.pdf, dpiit-nicdc-2025-11.pdf. Readings: 8. Range: 30 June 2025 to 30 June 2026.
What is being measured
The value the Government of India has approved for trunk infrastructure tender packages in the Activation Area. Approval is a sanction to spend, and it is the earliest of the three money events that matter. It is not a contract award figure, it is not a bill raised, and it is emphatically not money spent on the ground.
What this figure does not tell you
No expenditure-to-date figure for Dholera appears anywhere in these reports, so the gap between what was approved and what has been paid out cannot be measured here.
How the source words it
GoI has approved the tender packages for various infrastructure components amounting to Rs. X Crore divided into N packages for activation areaWording as it appears in the Delivery Monitoring Unit proforma. X and N stand for the printed figures.
Definition written by this register. The quantity, its unit and its date are the source's; the explanation is ours and carries no figures of its own.
No movement
This quantity did not change in any of the 8 readings held here, from 30 June 2025 to 30 June 2026. That is a finding rather than an absence of one: the same figure was re-published every time the report was issued. A register records repetition as carefully as it records movement, because a figure that has not moved in a year is the answer to a question people keep asking about this project.
Computed from the dataset by comparing consecutive published readings. Nothing is interpolated between two readings.
Related readings
| Quantity | Latest value | Unit | As on | Source |
|---|---|---|---|---|
| Approved package count | 5 | packages | 30.06.2026 | dmu-latest.pdf, p1 |
| Matching equity released | 2 784.83 | INR crore | 30.06.2026 | dmu-latest.pdf, p1 |
Latest reading for each related quantity, with its own date and source page.