Metric / approved-infrastructure-package-value

How much money has been approved for Dholera's roads, water and power?

Money approved for roads, water and power

This is the amount the central government has signed off for the main roads, water lines, drains and power network inside the first phase. Approval is permission to spend. It is not proof that anything has been spent, and this page keeps the two apart. The answer today is 2 784.83 INR crore, as at 30 June 2026. It has not changed once in the 8 monthly reports held here, going back to 30 June 2025.

01

The figure, and when it was published

Approved value of trunk infrastructure tender packages

2 784.83INR crore

Published for 30 June 2026 in dmu-latest.pdf, p1. The tag OFFICIAL means this is a figure the source itself prints, not one this site has worked out.

Approved tender package value. NOT expenditure incurred; the report gives no expenditure-to-date figure for Dholera.

Source: NICDC/DPIIT 'Proforma for Reporting to the Delivery Monitoring Unit - Industrial Corridor Projects', as-on 30.06.2026. Reference: dmu-latest.pdf, p1. Reading date: 30 June 2026.

02

Every published figure, in order

Approved value of trunk infrastructure tender packages, 8 dated readingsRecorded values between 30 June 2025 and 30 June 2026, in INR crore. Every plotted point is a published reading; nothing between two points is interpolated.2 4002 6002 8003 0003 20030.06.2531.08.2531.10.2531.01.2630.06.26REPORT DATEINR CROREApproved value of trunk infrastructure tender packages, 8 dated readingsRecorded values between 30 June 2025 and 30 June 2026, in INR crore. Every plotted point is a published reading; nothing between two points is interpolated.2 4002 6002 8003 0003 20030.06.2530.11.2530.06.26REPORT DATEINR CRORE
Each square is one published figure and the line simply joins them. Points sit at their true dates, so a wide gap across the page is a gap in the reporting rather than a slow month.

Approved value of trunk infrastructure tender packages: 8 dated readings

Approved value of trunk infrastructure tender packages: 8 dated readings
As onValueUnitAs printed in the sourceTagSource file and pageCK
30.06.20252 784.83INR croreRs. 2,784.83 CroreOFFICIALdmu-2025-06-30.pdf, p1
31.08.20252 784.83INR croreRs. 2,784.83 CroreOFFICIALdmu-2025-08-31.pdf, p1
30.09.20252 784.83INR croreRs. 2,784.83 CroreOFFICIALdmu-2025-09-30.pdf, p1
31.10.20252 784.83INR croreRs. 2,784.83 CroreOFFICIALdmu-2025-10-31.pdf, p1
30.11.20252 784.83INR croreRs. 2,784.83 CroreOFFICIALdpiit-nicdc-2025-11.pdf, p1
31.01.20262 784.83INR croreRs. 2,784.83 CroreOFFICIALdmu.pdf, p1
31.05.20262 784.83INR croreRs. 2,784.83 CroreOFFICIALdmu-2026-05-31.pdf, p1
30.06.20262 784.83INR croreRs. 2,784.83 CroreOFFICIALdmu-latest.pdf, p1
Standing reading2 784.83INR croreRs. 2,784.83 CroreOFFICIALdmu-latest.pdf, p1

Sources: dmu-2025-06-30.pdf, dmu-2025-08-31.pdf, dmu-2025-09-30.pdf, dmu-2025-10-31.pdf, dmu-2026-05-31.pdf, dmu-latest.pdf, dmu.pdf, dpiit-nicdc-2025-11.pdf. Readings: 8. Range: 30 June 2025 to 30 June 2026.

03

What this figure actually counts

The value the Government of India has approved for trunk infrastructure tender packages in the Activation Area. Approval is a sanction to spend, and it is the earliest of the three money events that matter. It is not a contract award figure, it is not a bill raised, and it is emphatically not money spent on the ground.

What this figure does not tell you

No expenditure-to-date figure for Dholera appears anywhere in these reports, so the gap between what was approved and what has been paid out cannot be measured here.

How the source words it

GoI has approved the tender packages for various infrastructure components amounting to Rs. X Crore divided into N packages for activation areaWording as it appears in the Delivery Monitoring Unit proforma. X and N stand for the printed figures.

Definition written by this register. The quantity, its unit and its date are the source's; the explanation is ours and carries no figures of its own.

04

Why it has not changed

This quantity did not change in any of the 8 readings held here, from 30 June 2025 to 30 June 2026. That is a finding rather than an absence of one: the same figure was re-published every time the report was issued. A register records repetition as carefully as it records movement, because a figure that has not moved in a year is the answer to a question people keep asking about this project.

Computed from the dataset by comparing consecutive published readings. Nothing is interpolated between two readings.

05

Figures worth reading beside this one

Readings that belong beside this one

Readings that belong beside this one
QuantityLatest valueUnitAs onSource
Approved package count5packages30.06.2026dmu-latest.pdf, p1
Matching equity released2 784.83INR crore30.06.2026dmu-latest.pdf, p1

Latest reading for each related quantity, with its own date and source page.