Dholera Progress Record

Register 01 / Vol 2026 / Readings through 04.08.2026

Last entry 30.06.2026
Metric / expressway-physical-progress

Metric / 2 dated readings

Ahmedabad to Dholera expressway, physical progress

Ahmedabad to Dholera expressway, physical progress was 95 percent for FY 2024-25, as reported in the FY2024-25 annual report, in the audited annual report. The same line is published for 2 reporting years here, from FY 2023-24. Each value below carries its source page and how it was extracted.

01

The standing reading

01

95percent

Ahmedabad to Dholera expressway, physical progress, as reported in the FY2024-25 annual report, tagged OFFICIAL. Recorded in dicdl_ar25.pdf, p21 (printed p10).

Described as '110 km, 4-lane', implemented by NHAI. Not a DICDL-executed project.

Source: Dholera Industrial City Development Limited, 9th Annual Report 2024-25. Reference: dicdl_ar25.pdf, p21 (printed p10). Reading date: as reported in the FY2024-25 annual report.

02

The series, reading by reading

02
Ahmedabad to Dholera expressway, physical progress, 2 dated readingsRecorded values between 31 March 2024 and 31 March 2025, in percent. Every plotted point is a published reading; nothing between two points is interpolated.406080100100 PERCENT31.03.2431.03.25REPORT DATE (AS ON)PERCENTAhmedabad to Dholera expressway, physical progress, 2 dated readingsRecorded values between 31 March 2024 and 31 March 2025, in percent. Every plotted point is a published reading; nothing between two points is interpolated.406080100100 PERCENT31.03.2431.03.25REPORT DATE (AS ON)PERCENT
Solid brass line and filled squares: readings as published. Dashed line: 100 percent. Points are placed at their true dates, so a wide gap on the horizontal axis is a gap in the reporting, not a slow month.
Ahmedabad to Dholera expressway, physical progress: 2 dated readings
As onValueUnitAs printed in the sourceTagSource file and pageCK
FY 2023-2451percentachieved 51% physical progressOFFICIALAR_FY2023-24.pdf, p19 (printed p13)
FY 2024-2595percentachieved 95% physical progressOFFICIALdicdl_ar25.pdf, p21 (printed p10)
Standing reading95percentachieved 95% physical progressOFFICIALdicdl_ar25.pdf, p21 (printed p10)

Sources: AR_FY2023-24.pdf, dicdl_ar25.pdf. Readings: 2. Range: 31 March 2024 to 31 March 2025.

03

What is being measured

03

The only percentage completion figure published for any project in either dataset. It belongs to a road built by the national highways authority, not by the development company, and it is reported second hand in the company's Board report. Two annual reports give two readings a year apart.

What this figure does not tell you

Physical progress in a Board report is a reported figure, not an audited one, and the same report describes the road with a lane count that contradicts the other source.

Definition written by this register. The quantity, its unit and its date are the source's; the explanation is ours and carries no figures of its own.

04

Movement

04

This quantity changed 1 time across the readings held here. Each row is a change between two consecutive published readings, so the change happened somewhere inside that window and cannot be dated more finely from these sources.

Ahmedabad to Dholera expressway, physical progress: every recorded change
BetweenFromToChangeUnitSource pages
31.03.2024 to 31.03.20255195+44percentAR_FY2023-24.pdf p19 to dicdl_ar25.pdf p21

Computed from the dataset by comparing consecutive published readings. Nothing is interpolated between two readings.

05

Related readings

05
Readings that belong beside this one
QuantityLatest valueUnitAs onSource
Expressway lane count6lanes30.06.2026dmu-latest.pdf, p1

Latest reading for each related quantity, with its own date and source page.